Paving Schedule Update Eff 9/21/22

line paint

9/21/22 UPDATE:  PHASE 3 PAVING WORK

Paving work has been completed and we are awaiting line painting.

9/2/22 UPDATE:  PHASE 2 PAVING WORK

Main Street from Hammond Lane to 1363-1367 Main Street: 

Milling 1.5" of roadway replace with 1.5" of top bituminous concrete. 

Sunday 9/11 paving will begin at 7:00 pm

ROAD WILL BE CLOSED DURING WORK.

Pleasant Street from Main Street to Village Street: 

Milling 1.5" of roadway replace with 1.5" of top bituminous concrete. 

Sunday 9/11 paving will begin at 10:00pm-5:00am.  Paving will resume on Monday 9/12 at 7:00pm until completion.

ROAD WILL BE CLOSED DURING WORK.

Village Street intersection of Pleasant:

Milling 1.5" of roadway replace with 1.5" of top bituminous concrete. 

Sunday 9/11 paving begin at 7:00pm.

ROAD WILL BE CLOSED DURING WORK.

Exchange Street from Island Road to Orchard Street:   

Milling 1.5" of roadway replace with 1.5" of top bituminous concrete. 

Paving will begin when Main Street paving is complete.

ROAD WILL BE CLOSED DURING WORK.

EXPECT DELAYS DURING THESE TIMES 

Upcoming Road Improvements - 2022

Paving Schedule for Summer and Fall 2022