FY27 Tentative Road Paving Schedule

paving

Road Work Update – Tentative Schedule

Please be advised of the following tentative roadway improvement schedule, weather/field conditions permitting:

Road Paving
July 1 & July 2: Baltimore Street and Norfolk Road
Morning of July 3: Morse Avenue and Causeway Street

Road Reclaiming
Beginning July 6: Van Kleeck Road and Cedar Street

Binder Course Paving
July 13 & July 14

Topcoat Paving
July 20–23

Residents and motorists should expect temporary traffic delays, lane restrictions, and construction equipment in the work areas during these operations. Please use caution, follow posted signage, and allow extra travel time.
Please note that all dates are tentative and subject to change due to weather conditions or other unforeseen circumstances. Updates will be provided, if necessary. Thank you for your patience and cooperation as we continue improving our roadways.